A manufacturer receives a large customer order with a delivery deadline three weeks away. The finished product requires several components, two subassemblies and multiple production operations. One work centre already has a full schedule, and a key raw material has a long supplier lead time.
The production planner needs to answer several questions:
How many units must the factory produce?
Which components must be purchased or manufactured?
When should replenishment begin?
Does the factory have enough work-centre capacity?
Which operations need to move when a machine becomes unavailable?
What happens when a required material does not arrive on time?
These decisions form the core of Odoo production planning. Within Odoo ERP for Manufacturing, Odoo Manufacturing connects demand, bills of materials, replenishment and work orders so planners can coordinate materials and production activities.
This guide explains how Odoo MRP handles the planning process, from calculating component requirements to scheduling operations and responding to shortages.
How Odoo MRP Turns Demand into Production Requirements
Material Requirements Planning (MRP) determines what materials and components a manufacturer needs to produce a specified quantity of finished goods.
In Odoo, the Manufacturing, Inventory, Sales and Purchase applications work together to provide the records used in this process. The planning cycle starts with demand. That demand can come from confirmed customer orders, forecast requirements or stock replenishment needs.
Odoo then uses product configuration, bills of materials, stock forecasts and replenishment rules to help determine which products and components need to be purchased or manufactured. The planner reviews the requirements, confirms the relevant orders and coordinates the production schedule.
Step 1: Start with Demand and the Production Requirement
Before creating manufacturing orders, planners need a clear picture of what the business must produce.
Demand can come from:
Confirmed sales orders.
Forecasted customer demand.
Minimum stock requirements.
Seasonal production plans.
Replenishment requirements for finished goods and components.
For example, a furniture manufacturer receives an order for 200 office desks due in four weeks.
The planner checks current finished-goods stock and existing manufacturing orders to determine how many additional desks the factory must produce.
If 30 finished desks are available and no other orders have reserved them, the production requirement is 170 units.
The planner then considers component availability, existing purchase orders, manufacturing lead times and work-centre schedules.
This is where Odoo production planning moves beyond a simple sales forecast. The required output must be supported by materials and available production resources.
Step 2: Use Bills of Materials to Calculate Component Requirements
A Bill of Materials (BoM) defines the components and quantities required to manufacture a product. It can also contain production operations and instructions.
For the office desk, the BoM might include:
One tabletop.
Four metal legs.
One support frame.
A set of fasteners.
Protective packaging.
If one desk requires four legs, producing 170 desks requires 680 legs.
Odoo uses the BoM to calculate the component requirements for a manufacturing order. It compares those requirements with stock availability and forecasted quantities to help the planner identify what needs replenishment.
Multilevel Bills of Materials
Some products contain subassemblies that must be manufactured before final assembly.
For example, a desk may require a preassembled support frame. That frame has its own BoM containing metal brackets, screws and connecting bars.
Odoo supports multilevel BoMs, allowing manufacturers to define the component structure across several production levels.
The planner can then manage the requirements for both the finished product and its manufactured subassemblies.
BoM Accuracy Affects the Entire Plan
An inaccurate BoM creates inaccurate material requirements.
If a desk requires four legs but the BoM lists three, Odoo's calculated requirement will be wrong. The same problem occurs when component quantities, units of measure, product variants or production operations are outdated.
Review BoMs whenever product designs, materials or manufacturing methods change.
For products with several variants, configure the correct BoM for each applicable variant or use the appropriate variant-specific component rules.
Step 3: Use Reordering Rules to Replenish Materials
Once Odoo calculates component requirements, planners need to ensure that the necessary materials arrive before production begins.
Reordering rules help maintain forecasted stock within defined minimum and maximum quantities.
For example, the manufacturer sets the following rule for metal legs:
Minimum quantity: 200 units.
Maximum quantity: 800 units.
Replenishment route: Buy.
When forecasted stock falls below the minimum, Odoo triggers replenishment according to the rule's configuration.
The replenishment route determines what Odoo creates:
Buy: A request for quotation is generated for the supplier.
Manufacture: A manufacturing order is generated for the product.
Automatic and Manual Reordering Rules
Odoo supports two reordering triggers.
Automatic replenishment creates a purchase or manufacturing order when the configured rule is triggered by forecasted stock falling below the minimum.
Manual replenishment lists the product on the replenishment dashboard. The planner reviews the required quantity, lead times and expected dates before placing the order.
Manual replenishment gives planners more control over purchase timing, supplier coordination and production priorities.
Why Lead Times Matter
A replenishment quantity alone does not guarantee that materials will arrive on time.
Planners must account for:
Supplier lead time.
Purchase confirmation time.
Manufacturing lead time.
Component preparation time.
Delivery deadlines.
Security lead times.
Odoo uses these lead-time settings to calculate planned dates for purchasing, manufacturing and delivery operations.
If a supplier needs ten days to deliver metal legs, the purchase order must be scheduled early enough to support the production deadline.
Step 4: Use the Master Production Schedule for Longer-Term Planning
Reordering rules help maintain stock thresholds. The Master Production Schedule (MPS) supports planning across future periods using demand forecasts and stock targets.
This is particularly useful for manufacturers with seasonal demand, long procurement cycles or products that require production well ahead of confirmed customer orders.
For example, a furniture manufacturer expects demand for office desks to increase before the start of a new academic year.
The planner can use the MPS to review monthly or weekly demand, starting stock, forecasted demand, replenishment quantities and forecasted stock.
How the MPS Calculates Replenishment
The MPS uses several planning values:
Starting Stock: The projected stock available at the beginning of the period.
Forecasted Demand: The quantity expected to be needed during the period.
Indirect Demand: Component requirements generated by the demand for manufactured products.
Replenishment: The quantity planned for purchase or manufacturing.
Forecasted Stock: The projected stock remaining after demand and replenishment.
The replenishment suggestion considers the safety stock target, starting stock and forecasted demand.
Planners can adjust forecasted demand and replenishment quantities to reflect their production plans.
MPS vs. Reordering Rules: When to Use Each
The two tools serve different planning needs.
Reordering rules maintain stock thresholds and trigger replenishment when forecasted stock falls below a configured minimum.
MPS helps planners manage expected demand across future periods and plan replenishment against stock targets.
Odoo's documentation specifically advises against applying reordering rules to the same products managed through MPS. Combining both methods for the same product can distort forecasts and create unnecessary replenishment.
Choose the replenishment method that matches the product's planning requirements.
The MPS also does not replace production scheduling. It helps determine what to replenish and when; work orders and work-centre planning handle the production operations.
Step 5: Check Work Centre Capacity Before Scheduling Production
Having enough materials does not mean the factory can produce the required quantity by the delivery date.
Production capacity depends on available machines, working hours, setup time, cleanup time, product capacity and the duration of each operation.
Odoo uses work centres to represent the locations or resources where manufacturing operations take place.
A manufacturer can configure:
Work-centre working hours.
Product-specific production capacities.
Setup and cleanup times.
Time efficiency.
Alternative work centres.
Hourly operating costs.
Allowed employees.
For example, the desk manufacturer has two assembly work centres. Each can assemble 20 desks per shift.
If the factory needs to assemble 170 desks, the planner must allocate enough production time across the available shifts.
A work centre with insufficient capacity becomes a bottleneck. Other operations may finish on time while the assembly queue continues to grow.
Account for Work Centre Availability
Work-centre calendars define when production resources are available.
Planners must account for machine downtime, scheduled maintenance and unavailable working periods when building the production schedule.
Odoo supports work-centre time off and alternative work-centre planning. When a work centre is unavailable, configured alternatives can help planners redirect operations.
Capacity planning should reflect actual production conditions. A machine's theoretical output does not account for setup, cleanup, downtime and operational constraints unless those factors are represented in the configuration.
Step 6: Schedule Work Orders on the Gantt Chart
After confirming manufacturing orders and their operations, planners need to decide when each work order will run.
Odoo's Manufacturing planning views include a Gantt chart that displays scheduled work orders along a timeline, grouped by work centre.
The Gantt view helps planners:
See which work orders are scheduled.
Review the workload assigned to each work centre.
Identify overlapping operations and overloaded resources.
Assign start dates to unplanned work orders.
Reschedule operations when production priorities change.
Review dependencies between operations.
For example, a desk's manufacturing process may follow this sequence:
Cut and prepare the tabletop.
Weld the metal support frame.
Apply the surface finish.
Assemble the desk.
Complete final inspection.
The assembly operation must wait for the required components and preceding operations.
Odoo can represent work-order dependencies so an operation starts after its prerequisite work is completed. The Gantt view displays these relationships and helps planners see the effect of rescheduling.
What Happens When a Work Order Moves?
Suppose the finishing work centre becomes unavailable for one day.
The planner reviews the scheduled work orders and moves the affected operation. Linked operations can be rescheduled according to the selected rescheduling behaviour.
Odoo provides options to preserve existing buffers, use available buffers or reschedule manually.
These buffers matter when operations require curing, cooling, drying or other waiting periods.
The planner must protect essential production intervals while adjusting the schedule to meet delivery commitments.
Step 7: Respond When Materials Run Short
Material shortages are one of the most common causes of production delays.
A component can become unavailable because of a late supplier delivery, unexpected scrap, higher-than-forecast demand or inaccurate inventory records.
Odoo provides stock forecasts, replenishment information and manufacturing-order component availability to help planners identify these problems.
Consider the desk manufacturer again. The production plan requires 680 metal legs, but only 500 are available and the supplier cannot deliver the remaining quantity for another week.
The planner needs to decide how to proceed.
1. Identify the Missing Components
Review the manufacturing order and its component availability. Check the forecasted stock, incoming receipts, existing reservations and expected delivery dates.
This establishes whether the shortage is temporary or whether the purchase plan needs to change.
2. Replenish the Shortage
If the missing material is purchased, use the Buy route and the relevant replenishment process to create or update the purchase order.
If the component is manufactured internally, review its BoM and production requirements and create the necessary manufacturing order.
3. Reallocate Available Materials
Review other production orders that require the same component.
The planner can adjust reservations and priorities to allocate available stock to urgent orders. This prevents a low-priority production run from consuming materials required for an urgent customer commitment.
4. Reschedule Affected Work Orders
If the missing component prevents an operation from starting, update the production plan.
Move affected work orders to reflect the expected material arrival date and adjust dependent operations accordingly.
5. Update Delivery Commitments
Review the effect of the shortage on finished-product availability and customer delivery dates.
The sales team needs accurate information about which orders remain on schedule and which require revised commitments.
Odoo provides the records needed to coordinate these decisions. The planner remains responsible for choosing the response and updating the production plan.
How to Keep the Production Plan Accurate
An effective production plan depends on reliable operational data. Even a well-configured MRP system produces poor schedules when its underlying information is inaccurate.
Manufacturers should review these areas regularly:
Bills of Materials: Keep component quantities, product variants and production operations aligned with current product specifications.
Inventory Records: Record receipts, consumption, transfers, scrap and adjustments accurately.
Supplier Lead Times: Update purchasing lead times when supplier performance changes.
Work Centre Calendars: Maintain accurate working hours, capacities and planned downtime.
Production Durations: Compare expected operation times with actual production records.
Demand Forecasts: Review historical demand, confirmed orders and seasonal requirements before updating the MPS.
Production Exceptions: Record shortages, delays, substitutions and changes that affect the production plan.
For a wider system-health review, see our Odoo Maintenance Checklist.
Common Odoo MRP Planning Mistakes
Using Inaccurate Bills of Materials
Incorrect component quantities lead to inaccurate material requirements. Review BoMs whenever engineering or production changes affect the product.
Applying MPS and Reordering Rules to the Same Product
Using both methods on the same product creates conflicting replenishment calculations. Select the planning method that fits the product.
Ignoring Supplier Lead Times
A component can appear in the replenishment plan without arriving in time for production. Include vendor lead times and purchasing preparation time in the plan.
Treating Work Centre Capacity as Unlimited
Scheduling work orders without considering working hours, product capacities and setup times creates unrealistic production dates.
Rescheduling Without Reviewing Dependencies
Moving one operation affects the operations that depend on it. Review linked work orders and required buffers before changing the schedule.
Treating a Shortage as an Inventory Problem Only
A material shortage affects purchasing, production priorities, work-centre schedules and customer delivery commitments. Resolve the issue across the entire order flow.
When Standard Odoo MRP Needs Customisation
Odoo Manufacturing provides tools for BoMs, manufacturing orders, work orders, replenishment, MPS, work centres and production planning.
Manufacturers with more specialised requirements may need additional planning logic. Examples include complex finite-capacity scheduling, advanced production sequencing, specialised constraint-based planning, supplier risk dashboards and automated exception alerts.
These requirements need to be assessed against the standard Odoo workflow before development begins.
Odoo customization services can extend planning workflows when standard configuration does not cover the required business logic.
Where production planning depends on external systems such as MES platforms, supplier portals, warehouse systems or machine data, Odoo integration services can connect the relevant applications.
Conclusion: Build a Production Plan That Reflects Your Factory's Reality
Effective production planning connects demand with material availability, purchasing lead times and work-centre capacity. A production schedule must reflect what the factory can actually produce, not just what the sales forecast requires.
Odoo production planning brings these records together through BoMs, replenishment rules, the Master Production Schedule, manufacturing orders and work-centre planning. If you would like help checking how your own demand, materials and capacity data would carry through an Odoo plan, you can contact us and talk through your manufacturing requirements.